Trace one month from the meter to the invoice https://reexasia.com/guides/power-purchase-agreement/ Energy produced, energy delivered and energy paid for can be different quantities. Follow the agreement’s delivery point, loss allocation and treatment of curtailed output before multiplying a tariff by generation. An illustrative settlement bridge A hypothetical project could generate 1,000 MWh in a month before curtailment. In this teaching example, curtailment prevents 80 MWh from being generated, leaving 920 MWh actually generated. Pre-delivery losses of 20 MWh leave 900 MWh delivered and payable at USD 60/MWh. Curtailed energy is not subtracted again from metered generation. Bridge itemQuantityEffect in this example Uncurtailed potential1,000 MWhBefore curtailment and delivery losses; not metered generation Pre-delivery losses−20 MWhExcluded by the assumed delivery-point rule Uncompensated curtailment−80 MWhExcluded by the assumed curtailment rule Payable energy900 MWh900 × USD 60 = USD 54,000 Multiplying the uncurtailed potential by the tariff would give USD 60,000, overstating this illustrative energy invoice by USD 6,000. If the actual agreement compensates deemed generation, pays a capacity charge or assigns losses differently, rebuild the bridge from those clauses. Do not insert the teaching assumptions into a real project model. A contract-to-model review Locate the metering and delivery-point clauses and identify each quantity’s evidence source. Locate dispatch and curtailment rules, exclusions, claim procedure and proof required for compensation. Separate energy charges, capacity charges, indexation, tax and currency terms. This example calculates only one energy charge. Distinguish the invoice from cash received. Apply the actual due date and payment-security terms when modelling liquidity. Ask the responsible legal and financial advisers to resolve uncertain interpretations before presenting the downside case. The World Bank resource explains common PPA structures and risk allocation across different project types. The numerical bridge above is original and hypothetical; it is not a ReEx transaction, financing offer or promise that a contract is bankable. Text equivalent: 1,000 MWh potential → −80 curtailment → −20 losses → 900 MWh payable → USD 54,000 Period and currency: __________________________ Meter/delivery point: __________________________ Uncurtailed potential and actual-generation evidence: __________________________ Loss allocation clause: __________________________ Curtailment and deemed-energy clause: __________________________ Payable energy calculation: __________________________ Tariff/indexation/capacity charges: __________________________ Invoice versus cash due date: __________________________ Security and downside case: __________________________ Open legal/model question: __________________________ Original engineering settlement bridge, not a plant drawing or a documented ReEx deal. Assumptions are fictional. https://ppp.worldbank.org/sector/energy/energy-power-agreements/power-purchase-agreements